Construction Updates

We have exciting news to share.  Construction continues on the High-Water Outlet Project!  Below you will find updates on the progress.

Construction Schedule

Landwehr Construction has been awarded the contract for construction of the High-Water Outlet on Lake Shamineau, and they have provided a preliminary construction schedule.  This schedule is subject to change and is dependent on weather, material availability, etc.  Click below for the schedule.

Read more

Update -
Week ending April 26

During the week ending April 26th, the service door was installed and the the siding installation was completed on the pump house.  Click below for more information.

Read more

Update -
Week ending April 19

During the week ending April 19th, the turf reinforcement mat was installed around the force main outlet structure, and seed and mulch was laid along the remaining areas along Pulaski Rd, Atlantic Rd, Highway 10 and the majority of Aztec Road.  For further information, click below.

Read More

Update -
Week ending April 12

Landwehr stripped Aztec Road to the subgrade and hauled out the excess material.  In addition, they installed fabric and gravel on Aztec Road.  Also, the siding on the three of the four outside walls of the pump house was completed.  Click below for more information.  

Read More

Update -
Week ending April 5

During the week ending April 5th, the outer walls of the pump house were wrapped, and the metal siding, soffit and facia were installed.  Click below for further information on current activities and the future schedule.

Read more

Update -
Week ending March 29

During the week ending 3/29/24, Landwehr installed the pump into the wetwell.  In addition, plywood was installed on the outside of the pump house and the roof trusses.  The underlayment and the all the shingles were also installed on the roof of the pump house. Click below for a full report and the schedule for the next two weeks. 

Read more

Update -
Week ending March 22

During the week ending 3/22/24, Landwehr installed the permanent culvert pipe at the Auger property.  The also continued to remove excess material from the site.  Click below for a full report and the schedule for the next two weeks. 

Read more

Update -
Week ending March 15

During the week ending March 15th, Landwehr worked on cleaning up the site.  In addition, concrete was poured for the driveway for the pump house and the final bollard in front of the transformer was installed.  For more information, click below.

Read more

Update -
Week ending March 8

During the week ending March 8th, Landwehr pressurized and tested the force main pipe, installed the final length of pipe within the pump house, cleaned out the force main outlet structure, and worked on the manholes.  In addition, the concrete was poured for the transformer pad, bollards and pipe supports.  For more information, click below.

Read more

Update -
Week ending March 1

During the week ending March 1,  CC Steel worked on jetting and televising the gravity flow pipe.  Landwehr backfilled in and around the foundation walls for the pump house, the concrete floor was installed for the plump station.  Click below for more information.

Read more

Update -
Week ending February 23

During the week ending February 23rd, Landwehr installed force main pipe along Aztec Rd toward Highway 10.  In addition, they poured the concrete for the foundation walls for the pump station.  Landwehr is also working on spreading topsoil over the top of the force main pipe, working on backfilling, and sweeping Aztec Rd.  Click below for more detail.

Read more

Update -
Week ending February 9

During the week ending February 9th, Landwehr installed forcemain piping along Aztec Road moving toward Shamineau Drive.  They also installed the components inside of the two manholes, installed forcemain in preparation for the footings of the pump house.  Click below for further information.

Read more

Update -
Week ending February 2

During the week ending February 2nd, Landwehr installed gravity flow pipe near Atlantic Rd, working toward Highway 10.  Landwehr is also working on the force main outlet structure near Highway 10 and is beginning to remove sand from the cofferdam area.  They are also working on installing force main piping going from the pump house and crossing Aztec Road.  Click below for the schedule.

Read more

Update -
Week ending January 26

After some time off for the holidays and cold weather, Landwehr is continuing to install force main pipe along Aztec Road.  They are also working on installing gravity flow pipe near Atlantic road and taking sheeting out of the lake.  Click below for the schedule of the next activities.

Read more

Update -
Week ending December 22

During the week ending December 22nd, Landwehr worked on installing gravity flow pipe and backwash pipe along Aztec Road, installing the wet well, installing the fish screen over the inlet structure and installing pipe from the wet well to the pump house.  Landwehr will not be working over the holidays and will resume work on January 8th. Click below for more detail.

Read more

Update -
Week ending December 15

During the week ending December 15th, Landwehr worked on installing gravity flow pipe at the inlet area and worked on the first manhole on Aztec Rd. They also completed earthwork along Highway 10 and continued installing the gravity flow and backwash pipe along Aztec Rd.  Click below for more detail.

Read more

Update -
Week ending December 8

During the week ending December 8, Landwehr Construction  They also worked in the inlet area to install the first section of pipe and excavate sealed manholes and cleaned up the inlet area.  They also installed force main pipe along Highway 10 and restored ditches along Highway 10. Missing traffic control signs have also been replaced. Click below for more information, pictures and schedule.

Read more

Update -
Week ending December 1

During the week ending December 1, Landwehr Construction installed force main pipe along Highway 10, installed the inlet structure and dewatered the inside of the cofferdam. They also worked in the inlet area to install the first section of pipe and excavate excess material.  Click below for more information.

Read more

Update -
Week ending Nov 26

During the week ending November 26th, Landwehr worked on installing gravity flow pipe and manhole along Atlantic Road, hauled excess material off site and restored ditches, installed force main pipe along the East side of Highway 10, and seeded areas of field along Pulaski Road.  Click below for more detail.

Read more

Update -
Week ending Nov 17

During the week ending November 17th, Landwehr installed gravity flow pipe along Atlantic Rd; restored ditched to plan grade and elevation; installed culvert at Pulaski and Atlantic and installed erosion control blanket.  Click below for more detail and the schedule for the next two weeks.

Read more

Update -
Week ending Nov 10

During the week ending November 10th, Landwehr assisted the boring contractor with earthwork needs, cut the pipe that was bored under Co Rd 203, finished the installation of the force main pipe bored under Highway 10, installed gravity flow pipe, and restored the ditch grade along Pulaski Rd.  Click below for the full update, pictures and the schedule for the next two weeks.

Read more

Update -
Week ending November 3

During the week ending November 3rd, Landwehr installed gravity flow pipe and a manhole along Pulaski Road; removed milled asphalt from Aztec Rd; began boring alongside Highway 10; and worked on lake inlet cofferdam and dewatering.  Click below for full update, pictures and schedule for the next two weeks.

Read more

Update -
Week ending October 27

During the week ending October 27th, installed gravity flow pipe along Pulaski Rd and prepared for boring operations.  Click below for more detail, pictures and a look ahead at work for the following two weeks.

Read more

Update -
Week ending October 20

During the week ending October 20th, the construction crew installed the sheet piling at the inlet in the lake to form the coffer dam so dewatering can begin.  They also installed a pump to remove the water from the interior of the coffer dam.  See attached report for more information, pictures and schedule.

Read more

Update - Week ending Oct 13

During the week ending October 13th, the Landwehr crew has been onsite mobilizing equipment and materials.  In addition, they began installing the new sheet piling at the inlet section of the piping.  An additional crew worked on installing the silt fend from the west side of Hwy 10 to the east side of Hwy 203.  See attached report for more information, pictures and schedule.

Read more

Update -
Week ending 10/6/23

During the week ending October 6, 2023 the Landwehr crew worked on constructing the causeway for the inlet structure.  They also cleared along the south side of Aztec road and removed and hauled out the building on the land that will be used for the pump house.  Click below for the full report and pictures.

Read more

Update - 
Week ending 9/29/23

During the week ending 9/29/23, Landwehr was on-site clearing the areas where they will be installing piping and future utilities.  Signs for the detour route were set and they milled the asphalt on Aztec Road.  Click below for the Contractor report.

Read more

Update -
Week ending 9/23/23

During the week ending 9/23/23, the Contractor mobilized material and equipment.  Stakes have been set and initial traffic control is taking place.  Click below for a full report and the schedule for the next two weeks. 

Read more

Gallery

We will periodically add pictures of the construction progress.

High Water Project Documents

Lake Shamineau water levels have been rising, causing shoreline erosion, loss of trees, wildlife habitat destruction, flooding of properties and causing millions of dollars of property damage and loss.  A high-water project has been developed with the purpose of establishing a maximum operating level for economic and natural resource benefits.  The project involves the construction of a permanent outlet for the lake to manage the high-water levels.  Click below for documents that provide further explanation of the project.

September 13, 2023

Houston Presentation at LID Board Meeting

August 18, 2023

DNR Climatology Report

June 27, 2023

Houston Presentation at Public Hearing

May 15, 2023

Houston Engineering Feasibility Report

April 9, 2023

High-Water Project Update

October 21, 2022

Lake Shamineau Elevation Readings

July 27, 2022

High-Water Project Update Meeting

June 28, 2022

High-Water Route Map

January 27, 2022

High-Water Project
Status Update

January 17, 2022

EAW Order of Decision

October 13, 2021

Authorization to Utilize
Todd Co. Ditch 41

August 5, 2021

High-Water Project Informational Meeting

August 7, 2020

Concept Report

September 24, 2019

Delegation of Authority for the HW Project by Morrison County

June 3, 2019

Engineers Report

January 23, 2018

Feasibility Report